Updated November 14, 2026: Added the November 14 Monarch electrician listing and its union-craft inquiry route. Other observations retain their stated dates.
Kiewit’s work reaches well beyond data centers. TIC holds the Smarr power plant EPC role in Georgia.[12] MWH-Kiewit is building Portland’s Bull Run filtration facility.[14] Kiewit Water Facilities South Co. lists an Orlando water project as awarded and seeking bids. Those are different teams and different routes to work.[1]
For contractors, the useful starting point is a named project team and its purchasing route. For tradespeople, it is the craft employer or union connected to that work. This report separates those paths across selected U.S. and Canadian projects, with sources checked November 6, 2026. It is a company work map, not a complete backlog or list of open jobs.
Where the work is moving
Power construction has a concrete non-campus lead in Georgia. Oglethorpe Power selected Kiewit subsidiary The Industrial Company (TIC) for its 1,425-megawatt Smarr Combined-Cycle facility in January 2026. The owner reported a ceremonial groundbreaking on May 7 and a $3.3 billion project investment, with operation projected for 2029. That is the owner’s project cost, not a disclosed TIC contract value.[12][16]
Water work has a recent field-workforce observation in Oregon. Portland’s November 2 report quotes the MWH-Kiewit filtration facility construction manager describing 485 craft workers on the Bull Run job. The city identifies the facility’s construction manager/general contractor as the MWH Constructors and Kiewit Corporation joint venture. That workforce observation is more useful than a broad hiring forecast, although it is not a vacancy count.[14]
Marine expansion is still a proposal. On October 22, HD Hyundai USA LLC and Kiewit Maritime Co. announced plans for HD Kiewit Shipbuilding LLC and a purpose-built U.S. shipyard. Construction is targeted for 2027 and full operations for 2029. The announcement describes a Gulf-access industrial site but does not identify the location. Treat this as a supplier-development lead, not a released construction package.[24][27]
Key Bridge is no longer a new-procurement route through Kiewit. Maryland told Kiewit Infrastructure Co. on April 28 that it would not retain the company for Phase 2 of the Francis Scott Key Bridge rebuild. MDTA said the proposed price exceeded its independent estimates, while Phase 1 foundation piles and the temporary trestle would continue. Kiewit’s project page says no new procurements are needed. Contractors should not carry the original award forward as evidence that Kiewit still controls the full rebuild.[13][3]
Which Kiewit entity belongs on your work list?
Kiewit describes itself as employee-owned and organized through a network of subsidiaries.[7] Its October 22 statement lists operations in the United States, Canada, Mexico, Guam and India. It reports 2025 revenue of $18.2 billion and 34,500 staff and craft employees. These are company disclosures, not figures independently audited for this report. The project sample below covers selected work in the United States and Canada.[17]
| Organization | Supported relationship or role | Why the name matters |
|---|---|---|
| Kiewit New Mexico Co. | Named with Clayco as general contractors for Jupiter’s first 855,000-square-foot portion; the announcement describes a joint venture.[17] | Use the campus team for building work, rather than assuming a power division controls it. |
| The Industrial Company (TIC) | Oglethorpe calls TIC a wholly owned Kiewit Corporation subsidiary and its Smarr EPC partner.[12] | The owner directs construction craft candidates to TIC’s board, separately from permanent utility employment. |
| Kiewit Infrastructure South Co. | TDOT selected it as I-55 construction manager; it also participates in Kiewit/Boh, AJV.[25][2] | Match the state and project team before sending qualifications. |
| Kiewit Water Facilities South Co. | Named on Kiewit’s Florida water-project opportunity page.[1] | Water pursuits and highway pursuits have different entity labels even within the same state. |
| Aecon Kiewit Nuclear Partners | General partnership between Aecon and Kiewit Nuclear Canada, with Aecon the lead partner, for Darlington’s execution phase.[18] | Do not substitute the separate U.S. nuclear entity or treat Aecon’s disclosed contract share as Kiewit’s revenue. |
| Kiewit Nuclear Solutions Co. | Named subsidiary and lead constructor for Oklo’s Aurora-INL project in the July 15, 2025 announcement.[10] | A master services agreement and planned deployment are not operating-reactor evidence. |
| Weeks Marine and acquired subsidiaries | Kiewit completed the acquisition on January 1, 2023; the announcement preserves independent branding.[11][19] | Marine, dredging and tunneling leads can sit under acquired brands rather than a Kiewit-branded hiring page. |
| Kiewit Maritime Co. | Described as an affiliate of Kiewit Offshore Services, Ltd., within the Kiewit family.[24] | Its proposed shipbuilding venture is a different relationship from the completed Weeks acquisition. |
The review did not inspect a shareholder register or establish ownership percentages across all these entities. A project participant, subsidiary, affiliate and joint venture are different relationships. For a contract, confirm the legal counterparty on the actual bid documents and agreement.
Project and work-route evidence map
The dates below describe the evidence or announcement, not a promise that a package remains available. The action column identifies the next useful check for a contractor or worker.
| Project and geography | Documented role and dated scope | Practical route and timing boundary |
|---|---|---|
| Smarr Combined-Cycle, Monroe County, Georgia | TIC is engineering, procurement and construction (EPC) partner. The May 7, 2026 owner release describes groundbreaking, a 2029 operating target and up to 1,200 workers at peak construction.[12][16] | Use TIC craft careers for construction work. Oglethorpe careers covers the separate forecast of about 30 permanent plant jobs. Peak staffing is not current hiring volume. |
| Bull Run filtration facility, east Multnomah County, Oregon | MWH-Kiewit is facility CM/GC. Portland’s November 2 report gives a future treatment capacity of 135 million gallons per day and a September 2029 completion target.[14] | Ask for the filtration-facility team and exact scope. Do not assign all connecting pipeline work to this JV from a facility award. |
| I-55 replacement, Memphis, Tennessee, to West Memphis, Arkansas | TDOT selected Kiewit Infrastructure South Co. on March 13, 2025. Its project page, checked November 6, still describes functional design and includes September 2026 public-meeting material.[25][26] | Follow TDOT’s project page and confirm package release with the CM/GC team. The original fiscal-2026 construction estimate does not verify a start. |
| I-10 Capitol Corridor, Baton Rouge, Louisiana | Kiewit/Boh, AJV is the named project team. James Construction Group is a major subcontractor, not a JV member. The opportunities page still displays a September 25, 2026 bid deadline.[2][28] | That deadline has passed. Use the project questionnaire and BuildingConnected route to ask about later packages; do not treat the page’s “currently soliciting” language as a live deadline. |
| Iron Bridge Grit Removal, Orlando, Florida | Kiewit’s page labels this Kiewit Water Facilities South Co. project “Awarded” and “Actively seeking bids” when checked November 6.[1] | Use the Central Florida questionnaire and BuildingConnected links. The page gives no visible bid deadline; obtain current documents before pricing. |
| Darlington New Nuclear, Clarington, Ontario | Aecon’s May 8, 2025 release confirms an alliance construction contract for the execution phase. The partnership scope includes project management, construction planning and execution.[18] | Identify the partnership’s buying or recruiting team. The release’s 2030 completion forecast is not a current craft requisition. |
| Memorial Stadium, Lincoln, Nebraska | Kiewit’s page, checked November 6, advertises a November 7 union-craft event without printing its year. The owner’s timeline places major teardown in December 2026 and completion in August 2028.[6][15] | Dated recruitment evidence, not a standing event invitation. Confirm any future event or current opening with the project employer or union. |
| Proposed U.S. shipyard, Gulf-access site not named | HD Hyundai and Kiewit Maritime announced plans on October 22, 2026, targeting construction in 2027 and operations in 2029.[24] | Monitor for a named site, finalized venture and procurement notice. The forecast of up to 3,000 jobs concerns full operating scale, not current vacancies. |
Canada extends the work map beyond power and transit
Kiewit’s April 27, 2026 account identifies Arlington Bridge deconstruction in Winnipeg and its first Canadian drinking-water treatment award in Cranbrook, British Columbia. It also describes ongoing Raglan mining work through the Kiewit-Nuvumiut Joint Venture, including open-pit mining, ore transport and aggregate crushing. These are company-reported roles; this review did not recover the new municipal contracts or their subcontract calendars.[5]
That Canadian account also records 2025 work on the decarbonization and air-separation-unit package for Linde Engineering at Dow’s Fort Saskatchewan site in Alberta, and the North Runway Program at Vancouver International Airport. The runway scope includes an asphalt overlay, drainage and LED edge lighting. Those details give industrial and civil firms specific experience to match, without turning the company’s portfolio into an open-bid list.[5]
Data centers: keep campus and generation roles separate
At Project Jupiter in Doña Ana County, New Mexico, the October 22 announcement names Clayco and Kiewit New Mexico Co. as general contractors for the first 855,000-square-foot portion, says their joint venture was selected in August 2025, and reports topping out. It does not allocate every electrical, mechanical, fire-protection or commissioning package. Nor does that building role establish Kiewit’s contract for the proposed fuel-cell power system.[17]
At PORTS-Pike in Piketon, Ohio, the International Brotherhood of Boilermakers’ July 28 account assigns Bechtel to the data-center portion and Kiewit to the power-generation facilities. Preserve that distinction when approaching either firm. The union article supplies role reporting, not an executed construction contract or an open procurement schedule.[21]
At Monarch in Mason County, West Virginia, Nscale’s June 18 announcement names Kiewit among employers working with it and participating in a June 30 job fair. That historical hiring event does not assign Kiewit a construction package or confirm a present opening.[22]
For the surrounding owner, permitting and work-route context, use Echelon’s separate reports on Project Jupiter, PORTS-Pike and Monarch Compute Campus. Their dated observations remain distinct from the company evidence reviewed here.
How subcontractors and suppliers should approach Kiewit
Start with the project route when one exists. The Central Florida page asks firms to complete a subcontractor questionnaire and create a BuildingConnected account; it says BuildingConnected handles bid solicitations, plans, specifications and addenda. The Baton Rouge JV likewise asks for its questionnaire and a BuildingConnected account. Those are documented entry processes, not proof that your trade has an unawarded package.[1][2]
The Baton Rouge contract-opportunities page shows why the deadline needs a separate check. On November 6 it still said bids were due September 25, 2026, at “1:00 PM CST,” alongside “currently soliciting” language. Its listed scopes include illumination, intelligent transportation systems (ITS), signals, welding, drainage materials and quality-control testing. Use that list to establish scope fit, then ask I-10CMAROutreach@Kiewit.com for the next applicable package and controlling documents. The displayed September deadline is past; no extension was established.[28]
The distinction matters within a single opportunity page. Florida’s Iron Bridge Grit Removal entry carries an awarded/bidding label, while its I-4 entries say “Awaiting RFP” and the clarifier replacement says “Not yet awarded.” Several other water entries say “TBD.” Do not treat those different stages as one list of live subcontract awards.[1]
For company-wide systems, Kiewit’s Business With Us page separates Source360 sourcing from Supplier360 profile updates for invited suppliers, and GEP purchase-order and invoice functions. It also tells contracted suppliers to work with their project contacts on invoice resolution. Use that page to reach the right system after identifying the buyer, rather than assuming a supplier profile creates a bid invitation.[8]
A useful capability statement should name the project, legal business, trade scope, operating region and relevant comparable work. Match its supporting documents to the buyer’s requirements. Kiewit’s Florida page specifically lists safety performance, quality, licenses or certifications, past performance, insurance and bonding capability among its evaluation criteria.[1]
Before accepting a purchase order or bank-detail change, use the verification route on Kiewit’s official supplier page. The company warns that fraudulent messages can include real employee names and office addresses, and says it no longer accepts email, PDF or paper forms for vendor account changes or onboarding. That is a practical payment-control check, not a finding about Kiewit’s payment performance.[8]
Where tradespeople can act
Lincoln: dated evidence of the project hiring team
Kiewit’s Big Red Rebuild page, rechecked November 6, advertises a November 7 recruiting event but does not print the year beside that date. The owner’s project timeline places major teardown in December 2026. This report retains the named participants as project leads, not an evergreen invitation to attend. Check the employer page for any later event and confirm current openings before making travel plans.[6][15]
The named subcontractors are E&K, Falewitch, Grunwald, Helm, Seedorff, W&W AFCO and Continental Fire Sprinkler. Named union participants include Iron Workers Local 21, Bricklayers & Allied Craftworkers Local 15, Steamfitters & Plumbers MO/KS/NE Local Union 464, Carpenters Locals 427 and 1306, Operating Engineers Local 571, Laborers Local 1140, Sheet Metal Workers Local 3, Plumbers Local No. 16 and Sprinkler Fitters Local 669. These are event participants, not a complete employer roster or a promise of dispatch.[6]
Georgia: separate construction hiring from plant operations
Oglethorpe’s May announcement directed boilermakers, pipefitters and electricians toward TIC craft careers and said recruitment was planned to begin in June. That date is a historical plan. The board was reachable during this review, but the attempted Forsyth search did not establish a specific Smarr craft opening. Search the exact location and ask the recruiter to confirm the project, employer, start date and travel terms.[16][20]
Choose the application route for your trade and location
For other locations, Kiewit’s skilled-craft page separates civil, electrical/instrumentation, pipe, structural/ironworker, mechanical, operator and supervision work. It also publishes text-to-apply numbers: (402) 542-6851 for the United States and (587) 209-5552 for Canada. These are employer application routes, not a promise of placement or a project assignment.[9]
Kiewit’s union-craft opportunities page provides a more specific lead. On November 6, its Homer City Redevelopment section listed equipment operator journeyman, laborer foreman, pipefitter journeyman and water truck driver roles in Pennsylvania. The page offers an expression-of-interest form and directs workers to their local hall for union opportunities. It does not give pay, dispatch terms or confirmed remaining headcount. Obtain those details and the exact employer before committing to a move.[29]
Kiewit’s union-craft page also listed an electrician journeyman opportunity at Monarch Compute Campus in Point Pleasant, West Virginia, when checked November 14, 2026. Use the official union-craft route to ask about the employer, pay, dispatch requirements and remaining positions before traveling. The page does not state when this listing opened.
Ownership changes and the limits of the growth story
Kiewit completed its acquisition of Weeks Marine, Inc. on January 1, 2023. The deal included Healy Tibbitts Builders, Inc., McNally International, Inc. and North American Aggregates. Kiewit and Weeks both announced the closing for an undisclosed amount, with independent branding retained. Marine and tunneling leads therefore warrant separate searches under those brands. This was not a new 2026 acquisition.[11][19]
The October 2026 shipbuilding proposal is different. It is a planned joint venture involving HD Hyundai USA LLC and Kiewit Maritime Co., rather than evidence that Kiewit acquired HD Hyundai or that an operating shipyard already exists. For an equipment supplier, fabricator or workforce partner, the next useful evidence would be the site, delivery organization and released purchasing requirements.[24]
Echelon’s assessment: Kiewit is worth tracking by operating company and work package, not as a single data-center contractor. The selected evidence spans active field work, preconstruction, recruitment, a proposed new business and a lost next-phase role. It does not establish company-wide expansion or contraction, acquisition appetite, available bonding capacity or future workload for a particular trade.
Sources, scope and updates
This report uses project-owner and transportation-agency records, company and joint-venture pages, employer routes, union reporting and independent trade coverage. Sources were retrieved November 6, 2026; individual event dates are retained beside the claims. Company forecasts and portfolio descriptions remain attributed. The map is a selected review across sectors, not a census of Kiewit’s projects, subsidiaries, licenses, litigation or employment.
The review did not verify a complete legal ownership chain, current subcontract awards, wage schedules or open craft requisitions for every project. It did not audit group-wide safety or payment performance, and no company-wide layoff conclusion is supported. No applications, supplier registrations or inquiries were submitted. Before spending estimating time or traveling, use the official route to confirm the exact scope and current status.
For a correction or to supply additional information, contact Echelon Reports with the company name, project, relevant date and a public document or official link. New information is checked before it is added.
Sources
- [1] Central Florida Projects – Kiewit Corporation
- [2] Home | Kiewit/Boh, AJV
- [3] MDTA Key Bridge Rebuild – Kiewit Corporation
- [5] Kiewit's 85 Years in Canada – Kiewit Corporation
- [6] Big Red Rebuild – Kiewit Corporation
- [7] About Kiewit – Kiewit Corporation
- [8] Business With Us – Kiewit Corporation
- [9] Skilled Craft Professionals – Kiewit Corporation
- [10] Oklo Selects Kiewit as the Lead Constructor for First Aurora Powerhouse in Idaho – Kiewit Corporation
- [11] Weeks Marine organization joins Kiewit – Kiewit Corporation
- [12] Oglethorpe Power Selects Kiewit Subsidiary, The Industrial Company (TIC), as EPC Partner for New Monroe County Combined-cycle Plant – Oglethorpe Power
- [13] Maryland Transportation Authority to ‘Off-Ramp’ Progressive Design-Build Contractor for Key Bridge Rebuild Project | MDTA
- [14] Bull Run Filtration Project earns top safety recognition | Portland.gov
- [15] Project Overview | Big Red Rebuild
- [16] Oglethorpe Power Breaks Ground on New Monroe County Combined-Cycle Energy Facility – Oglethorpe Power
- [17] Clayco and Kiewit Reach Major Construction Milestone at Project Jupiter Data Center Campus – Kiewit Corporation
- [18] Aecon-led partnership awarded contract by Ontario Power Generation for the execution phase on the Darlington New Nuclear Project
- [19] Weeks Marine, Inc. joins Kiewit Corporation – Weeks Marine
- [20] TIC
- [21] Portsmouth Consortium Data Center to employ skilled trades | International Brotherhood of Boilermakers
- [22] Nscale to Host Monarch Compute Campus Job Fair Connecting Job Seekers with Careers and Training | Nscale
- [24] HD Hyundai and Kiewit Announce Plans for Next-Generation
- [25] Construction Manager Selected for I-55 Bridge Replacement Project
- [26] America’s River Crossing Bridge Replacement (I-55 Bridge)
- [27] HD Hyundai, Kiewit Plan New Joint Gulf Coast Shipyard – The Waterways Journal
- [28] Contract Opportunities | Kiewit/Boh, AJV
- [29] Union Craft Opportunities – Kiewit Corporation