Columbia wastewater expansion: contractors, packages and the Spring Hill connection

Project report · Columbia and Spring Hill, Tennessee
Reporting checked November 6, 2026

Columbia, Tennessee, is building a wastewater treatment plant with Judy Construction as construction manager.[6] The city expects completion in 2027 and says the new plant will increase Columbia’s treatment capacity to 17 million gallons per day.[26] A separate connection projected to cost about $12 million with Spring Hill adds a second route for contractors: a sewer force main and pump-station improvements, with responsibilities split between the two cities.[11][30]

For a subcontractor, the distinction matters. The treatment plant already has a construction manager and documented package awards.[6] The Spring Hill connection has an approved engineering assignment and interlocal approvals.[10][30] No open construction solicitation for that connection was identified on the two cities’ public bid boards on November 6, 2026.[28][29]

For the wider sector, see Echelon’s water and underground infrastructure guide.

Scope, buyer and decision status

Research reviewed November 6, 2026. Use this decision sheet to match your specialty to the responsible buyer before requesting current drawings. It separates approved contracts, planning estimates and proposed work. Amounts overlap and should not be added.

Scope and buyer Dated position Next document or answer to request
Columbia plant: Judy Construction, construction manager at risk Council approved a construction award not exceeding $95,279,796 on February 8, 2024. Wauford reports three package awards.[24][6] Current package buyout list, qualification requirements and drawings. Historic awards do not identify remaining work.
Spring Hill upstream connection: City of Spring Hill July 6 engineering authorization up to $530,000; October 19 approved connection plan. About $9 million of the projected $12 million plan covers connecting infrastructure.[10][30] Executed agreement, TDEC written authorization, final design and issued construction notice. Execution and final authorization are not confirmed here.[11]
Carter’s Creek pump-station upgrade: City of Columbia Agreement text assigns Columbia the work and caps Spring Hill’s contribution at $3 million unless both cities amend it.[11] Current scope and procurement record. The contribution cap is not a construction award.
Industrial Park Road force main: City of Columbia November 5 study-session packet requests ratification of $557,990.77 in emergency work by Judy, involving about 1,000 feet of 24-inch main.[25] Adopted minutes and completion record. This is separate collection work, not a new plant package.
Collection-system master plan: City of Columbia November 5 packet proposes a $100,000 engineering agreement with Water Management Services, LLC.[25] Council action, signed agreement and resulting upgrade recommendations.
Sewer collection rehabilitation: City of Columbia November 5 packet proposes $153,000 in engineering with Water Management Services, based on a $2 million citywide rehabilitation project.[25] Council action, approved plans and construction notice. The packet does not establish a construction award or a trenchless method.

The earlier November 6 public-board observations below did not identify an open interconnection solicitation. They do not cover private quotation requests.[28][29]

The $75 million state loan announced in August 2026 belongs to a different project.[3] TDEC identifies it as Drinking Water State Revolving Fund financing for Columbia Power and Water Systems, adding 12 million gallons per day at its drinking-water plant.[3] It is neither the wastewater plant’s construction price nor financing for the Spring Hill sewer connection.[3]

What the plant contract covers

On February 8, 2024, Columbia City Council approved an award to Judy Construction for the wastewater plant expansion in an amount not to exceed $95,279,796.[24] At the same meeting, council approved a $1,902,250 amendment for J.R. Wauford & Company’s engineering services.[24]

The construction award and engineering amendment total $97,182,046. That sum is not the final project cost: the construction amendment allows additions and deductions through change orders.[18][24]

The construction arrangement is CMAR, meaning construction manager at risk. Wauford identifies Judy in that role, while the city’s contract uses “Construction Manager as Constructor.” The city’s February 2024 material traces acceptance of Judy’s proposal to November 10, 2022, followed by the underlying agreement dated January 19, 2023.[6][18]

Wauford describes an oxidation-ditch extended-aeration process with biological nutrient removal. Its undated update reports work on treatment structures, including an anaerobic reactor, oxidation ditches and clarifiers. The page does not establish current field progress.[6]

Match your specialty to the documented packages

The January 11, 2024 guaranteed-maximum-price attachment divides construction into nine bid packages, plus process equipment.[18] Match a package number to your own work, then ask Judy who controls its current purchasing. The reported awards come from Wauford’s undated project page; no current buyout record was obtained.[18][6]

Package Documented scope Reported award and next question
1 Initial grading.[18] Harness, LLC: $1,995,861.92.[6] Ask whether any later grading phase needs quotations.
2 Piping, structural concrete and precast structures.[18] Judy Construction: $46,186,500.[6] Ask who handles any remaining supplier or subcontract scope.
3 Electrical.[18] Trans Electric Company: $10,507,492.[6] Ask the current buyer about installation and start-up requirements.
4 Miscellaneous metals.[18] Current award not established. Ask which fabrications remain to be purchased.
5 Building construction.[18] Current award not established. Request the current building scope and buyer.
6 Equipment installation.[18] Current award not established. Confirm installation responsibility and sequencing.
7 Painting and coatings.[18] Current award not established. Request the coating specifications and package status.
8 Site concrete, paving, fencing and final grading.[18] Current award not established. Ask about remaining areas and access restrictions.
9 Demolition and associated site work.[18] Current award not established. Request current limits and sequencing.

An unknown award in this table means the reviewed records did not establish it, not that the package remains open. The GMP attachment also lists process equipment separately. Its allowances and Wauford’s award figures are different records; their differences are not verified savings.[18][6]

Some exclusions also matter when pricing adjacent work. The January 2024 attachment excludes bypass pumping for tie-ins, new electrical service by Columbia Power and Water, and fire-prevention or sprinkler systems.[18] Confirm the current drawings and amendments before assuming those tasks are included, excluded or still available.[18]

The Spring Hill connection: pipe, pumps and a separate approval path

Spring Hill’s October 19 announcement describes a 12-inch sewer main from its reclamation plant on Mahlon Moore Road to Columbia’s system.[30] The proposed route follows Mahlon Moore Road and then a TVA easement for several miles.[30] The cities describe a flow range of 500,000 to 1.5 million gallons per day.[30]

Spring Hill had already approved engineering work on July 6, 2026.[10] Resolution 26-193 authorizes a task order of up to $530,000 with J.R. Wauford & Company, Consulting Engineers, Inc. (Ardurra).[10] Its supporting memorandum describes approximately 23,600 linear feet of 12-inch force main and associated pumping facilities, plus evaluation of improvements to the main sewage pumping station at Spring Hill’s plant.[10]

A force main carries wastewater under pressure from a pumping station. Here, the useful specialty match is pressure sewer construction, pumping equipment and the associated electrical and controls work. The agreement text also identifies meters, valves, telemetry and crossings among the interconnection facilities.[11]

The October meeting agreement assigns Spring Hill responsibility for designing, permitting, procuring, constructing and commissioning the facilities upstream of the delivery point.[11] Columbia is responsible for designing, permitting, procuring and constructing its pump-station upgrade.[11] Spring Hill’s contribution to that upgrade is capped at $3 million unless both cities approve a written amendment.[11]

That split gives contractors two buyer routes rather than one combined $12 million plant contract. It also makes the approval sequence important. The agreement text conditions implementation on TDEC’s written authorization, and Columbia says service starts only after the new treatment plant and required pump-station improvements are complete.[11][26] A final TDEC authorization and an executed agreement establishing the effective date are not confirmed here.[11][26]

The 23,600-foot alignment is a design description, not a guaranteed final quantity. The agreement permits changes for engineering, permitting and field conditions.[11] No particular trenchless method is established by these records.[11] Confirm the method in the final plans. For the differences in crew work, see Echelon’s trenchless methods and crew work guide.

The agreement gives Columbia until 24 months after the effective date or the established date of substantial completion of its treatment-plant expansion, whichever is later, to complete the pump-station upgrade.[11] With the effective date unconfirmed, that formula does not yield a verified calendar deadline. The city’s expected 2027 plant completion is not a confirmed connection opening date.[11][26]

Where contractors can act now

Start with Judy’s Columbia project page and its company contact route. Identify the Columbia, Tennessee wastewater CMAR project, your specialty and the package you can support. Ask for the person handling current subcontractor buyout or purchasing, then request the applicable qualification requirements and current documents.[23][16]

Send a short capability statement rather than an unsolicited price against the 2024 estimate. Include relevant treatment-plant or pressure-sewer experience, the scope you self-perform and the crew or equipment you can make available. Request confirmation of the package’s status before investing in a detailed takeoff.

For city-led work, Columbia’s bids and requests for proposals page directs vendors to BidNet Direct.[27] Its public agency page displayed no open bids on November 6.[28] Judy’s own current bid list showed a Morganfield, Kentucky project, not a Columbia solicitation, on the same date.[21]

Spring Hill’s public bid board displayed two open construction listings: city-hall security glazing and a Miles Johnson water-booster-station pump addition.[29] Neither was the Columbia wastewater interconnection.[29] These dated public listings do not establish whether a construction manager is privately requesting quotations or whether an unlisted package has been awarded.[29]

For the interconnection, ask the responsible city for the current design and permitting position, the procurement method, the anticipated bid release and any qualification or mandatory meeting requirements. Keep the Spring Hill force main and Columbia pump-station inquiries separate. No current submission deadline for either scope is established in this report.

For tradespeople

Judy’s employment page provides English and Spanish applications, but it is a general company route, not a verified Columbia vacancy.[15] Ask the employer to confirm the project assignment, employing contractor, start date, pay and travel terms. No project-specific wage or available headcount is established here.

For broader employer comparisons, Echelon’s underground utility contractor guide explains different company specialties. Columbia’s treatment structures and equipment packages call for a different experience mix from the inspection and lining roles in the sewer rehabilitation guide.

How this report was prepared

Echelon Reports compared council minutes, engineering attachments, city announcements and contractor pages. The decision sheet is an independent summary of public records, not an owner-certified bid register. Public-board entries retain their November 6 observation date and cover only the listings visible on those routes.[28][29] Executed agreement dates, final TDEC authorization and remaining subcontract buyout are still unconfirmed.

Sources

  1. [3] TDEC: $75 million drinking-water loan, August 17, 2026
  2. [6] J.R. Wauford: Columbia WWTP scope and package awards
  3. [10] Spring Hill Resolution 26-193 and engineering memorandum, July 6, 2026
  4. [11] Spring Hill October 2026 meeting: interlocal agreement text (unsigned)
  5. [15] Judy Construction: employment applications
  6. [16] Judy Construction: contact information
  7. [18] Columbia February 8, 2024 council packet: GMP, pages 239–256
  8. [21] Judy Construction: current bid list
  9. [23] Judy Construction: Columbia wastewater CMAR project
  10. [24] Columbia March 14, 2024 packet: February 8 minutes, page 97
  11. [25] Columbia November 5, 2026 study-session packet, pages 14–15 and 33
  12. [26] Columbia: approved interlocal agreement, October 13, 2026
  13. [27] Columbia procurement route
  14. [28] Columbia public bid list, observed November 6, 2026
  15. [29] Spring Hill public bid list, observed November 6, 2026
  16. [30] Spring Hill: interlocal wastewater plan adopted, October 19, 2026

Echelon Trades Jobs

Hiring or looking for work in the trades?

Employers can submit an opening for review. Tradespeople can tell us what work they want. Both are free, and worker profiles stay private.

Post a free job Tell us what work you want

Visit Echelon Trades Jobs