Faith Technologies Incorporated (FTI) combines electrical construction with factory-built assemblies and power-distribution products. Its Excellerate expansion reaches beyond the jobsite: Indiana and Louisiana announced separate 500,000-square-foot manufacturing projects in 2026, while Alabama announced the conversion of a former distribution center.[12][17][42] For suppliers, that creates two different conversations: supporting factory production and supplying a specific construction project.
The commercial distinction matters. FTI’s published supplier purchase-order terms allow 75 days after invoice receipt for undisputed payment, less applicable retention, and a 2% discount for payment within 30 days. Excellerate Products’ customer terms generally require payment within 30 days of its invoice date, unless it specifies otherwise in writing. Aftermarket parts are payable at order unless otherwise authorized in writing.[22][7] Use the document for the direction of your transaction, then reconcile it with the issued order.
This supplier guide covers FTI’s factory and field work, the terms to review before quoting and the documents to request from a buyer. Start with supplier access and order terms, compare the manufacturing locations, or go directly to jobs and apprenticeship. Research checked November 9, 2026. Announced investment, projected hiring and historical project work retain their own dates below.
FTI, Faith Technologies and Excellerate: which name matters?
FTI lists its headquarters at 201 Main Street in Menasha, Wisconsin.[27] Its roots are in Town & Country Electric, founded in Appleton in 1972. FTI says Faith Technologies Incorporated became its primary brand in 2021.[9]
These names describe different parts of the business. They do not establish separate legal subsidiaries. Excellerate Products’ terms name Faith Technologies Incorporated doing business as Excellerate Products.[7] The apprentice listing names Faith Technologies, Inc. as the hiring organization.[47] Use the exact buyer or employer name in your paperwork. Do not assume each brand is a separate buyer.
| Name or activity | Supported role | How to frame your inquiry |
|---|---|---|
| FTI / Faith Technologies | Electrical planning, engineering, construction and installation. The service menu checked on November 16, 2026 lists Electrical, Systems Integration and Power Solutions among its categories.[12][29] | Identify the site, trade package and whether your work is installation, controls, commissioning or service. |
| Excellerate | Manufactured electrical assemblies and modular construction. Indiana describes complete modular electrical buildings for data centers and other mission-critical facilities.[12] | State whether you supply components to a factory or install an assembly at its destination. Ask for the responsible procurement team. |
| EnTech Solutions | FTI’s history identifies EnTech as its clean-energy brand, launched in 2020.[9] | Describe the energy asset and service needed. Do not infer a separate contracting entity from the brand. |
| Excellerate Products | An original equipment manufacturer (OEM) brand. The April 7, 2026 launch announcement identifies UL 891 low-voltage switchboards as its first product to market.[5] | Separate buying a finished switchboard from supplying its components. Request the applicable specification, commercial terms and service responsibilities. |
Updated November 16, 2026: FTI’s official service index lists Electrical, Systems Integration and Power Solutions.
FTI’s history dates the start of Excellerate Products to 2025. Its public launch announcement is dated April 7, 2026.[9][5] Those are different milestones.
How suppliers and subcontractors can approach FTI
FTI’s official contact form separates Services & Solutions, Products, Careers/Human Resources/Talent and Other. Product choices include UL 891 LV Switchboards, Power Module 2 MW and eSkid.[27] It is a general inquiry route, not a public supplier-approval portal. No open package list or company-wide subcontractor qualification questionnaire was verified for this guide.
Ask the contact team to send your supplier inquiry to the buyer for a named plant or project. State what you make or install, where you work and which certifications you hold. Explain how your scope fits the job. Do not send banking records or private financial statements through a general inquiry form.
An inquiry can be short: “We supply [component or trade] for [application] in [territory]. We are asking about [named FTI facility or project]. Who owns supplier qualification and purchasing for that scope, and which legal entity would issue the order?” This is a suggested inquiry, not an FTI-required form.
For Louisiana businesses, the state announcement also points to Source Louisiana as a statewide route into development-project contract and vendor pipelines.[17] Registration is distinct from FTI approval or an invitation for its Monroe facility.
A quote-to-order screen based on FTI’s terms
The screen below covers FTI’s live supplier terms reviewed November 9. The terms index links this document separately from Excellerate Products’ customer terms.[28][22] Do not rely on the indexed PDF under a 2021 upload path alone. The live page adds rules for invoices, capacity planning and product changes.[6][22] Ask the buyer which version forms part of your order. This screen helps you review a quote. It is not legal advice or a record of how FTI pays its bills.
| Exposure in the published supplier terms | Document or decision needed before commitment |
|---|---|
| Starting services or acting toward delivery can accept the order terms. The buyer rejects seller terms, and modifications require its written consent.[22] | Resolve exceptions in writing before production, shipment or site mobilization. A qualification attached to your quotation may not settle the conflict. |
| Forecasts are nonbinding and are not orders or purchase commitments, yet the terms require capacity, materials and parts sufficient to meet them.[22] | Agree on firm releases, reserved capacity and responsibility for unused inventory. Keep a planning forecast separate from a funded order. |
| Suppliers must submit invoices within 90 days after delivery or service completion, unless the order specifies otherwise. The page also disclaims an obligation to pay charges not invoiced within 120 days after acceptance.[22] | Record delivery, completion, acceptance and invoice submission separately. Resolve the applicable trigger before billing; include the buyer’s PO number and required invoice details. |
| Undisputed payment is due within 75 days of invoice receipt, less retention. Payment within 30 days earns the buyer a 2% discount. Withholding grounds include defective goods, late delivery and other breaches.[22] | Price the cash cycle, discount and retention. Obtain the submission address and evidence of receipt. Do not promise a payment date from delivery alone. |
| Delivery is FOB destination unless agreed otherwise, meaning delivery to the buyer’s destination. Under these terms, risk of loss remains with the seller until the buyer receives and accepts the goods. Delay can bring cancellation, actual or liquidated damages, expedited freight and substitute-purchase costs.[22] | Set delivery dates, inspection criteria, freight responsibility and delay remedies in the order. Escalate a known delay in writing immediately. |
| Division-specific quality requirements are available on request. The supplier must provide 90 days’ prior notice for specified manufacturing-location, material, method or critical-component changes.[22] | Obtain the relevant quality requirements before pricing. Map change-control duties to your own factories and upstream suppliers. |
| Product changes and end-of-life notices require at least 210 days’ advance notice; changed goods require written consent before shipment. A separate provision calls for replacement components for at least five years after the agreement ends.[22] | Check whether your manufacturer’s lifecycle policy can meet these obligations. Agree on last-time buys and replacement support before accepting a short-lived component. |
| The stated warranty is 18 months from installation. The page separately addresses latent defects and allows repair or replacement at seller expense. Failure to respond within three calendar days of written notification permits buyer-arranged replacement at seller expense.[22] | Reconcile the installation trigger with upstream warranties and preserve a staffed defect-response route. Review labor and replacement-cost exposure, not just the part price. |
| Site-specific insurance requirements apply where present. Otherwise, the page requires primary, noncontributory coverage, additional-insured endorsements and specified limits, including $1 million general liability per occurrence and $2 million umbrella per occurrence and aggregate.[22] | Have your broker review the full insurance section, required endorsements and duration. A certificate alone does not settle every coverage requirement. |
| The buyer can terminate for convenience. Recovery is limited to stated reasonable incurred costs and services in progress, capped at the order price; lost profits and specified consequential or incidental losses are excluded from buyer liability.[22] | Negotiate treatment of custom materials and work in process before committing. Keep supporting cost records. |
| Subcontracting requires prior written buyer consent. The terms also address indemnity, intellectual property, publicity restrictions, Wisconsin dispute venue and conditional federal-contract requirements.[22] | Send the complete order and incorporated documents for contract review. Obtain written permission before naming the customer or project in marketing. |
The live supplier page contains duplicate “Inspection” headings and visible editing markers in some clauses.[22] Request a clean controlling copy rather than silently interpreting those defects. The page says its terms can change without notice, which makes a retained, agreed version useful for both sides.[22]
Supplier decision record: factory, field or finished product
Copy these five questions into your bid notes. Record the confirming document, the buyer’s name and the date beside each answer. Leave unanswered fields marked “unknown” until the responsible party confirms them. This is a working checklist, not an FTI qualification form.
| Question to settle | Source-backed example and what to record |
|---|---|
| What are we supplying, and to whom? | Excellerate Products identifies FTI doing business under that name; the supplier and customer documents govern opposite transaction directions.[7][22] Record the issued buyer name, your scope and the applicable document. |
| Which site and construction phase? | Opus identifies FTI as general contractor for the Pittsboro factory and Opus as the site-infrastructure provider.[48] Record the facility, phase, package contact and invitation status. |
| Where does factory work end and field work begin? | FTI’s Little Chute case study describes factory-built modular electrical buildings for data centers.[49] Record who supplies, transports, installs, tests and accepts your scope. |
| Which quality and change rules apply? | FTI’s supplier terms offer division-specific quality requirements on request and require advance notices for manufacturing and product changes.[22] Record the controlling specification and any written exceptions. |
| What authorizes spending and starts the invoice clock? | The terms distinguish nonbinding forecasts from orders, require invoice submission within 90 days of delivery or service completion unless otherwise specified, and include a separate 120-day acceptance-based limit.[22] Record the firm order, agreed terms, acceptance evidence and invoice-receipt route. |
An unresolved buyer, scope boundary or order version is a reason to seek clarification before committing inventory or crew time. Use the longer terms screen above with the actual order, rather than treating a completed checklist as approval.
Manufacturing expansion: separate the locations and milestones
A manufacturing facility can supply distant projects. Its address does not identify the final installation site, and its investment announcement does not disclose unawarded packages. The selected developments below are separate projects, not a count of all FTI facilities. FTI also documents an established manufacturing base: its Little Chute, Wisconsin case study says the 385,000-square-foot facility was completed in November 2023. It names Boldt as general contractor and McMahon Associates as engineer.[49] That completed project is a capability reference, not one of the new developments listed below.
| Location | Dated evidence and practical meaning |
|---|---|
| Pittsboro, Indiana | On April 9, 2026, Indiana announced a planned $67.5 million investment in a 500,000-square-foot facility on 47 acres. Construction was underway; the state forecast up to 200 jobs by the end of 2027. The facility is intended to support Excellerate modular electrical production.[12] No completion or operating-start confirmation was found in this review. |
| Monroe, Louisiana | Louisiana’s June 9, 2026 announcement describes an $80.5 million, 500,000-square-foot facility at 535 Highway 594. Construction was underway, with completion and operations expected in spring 2027. It forecasts at least 200 direct jobs and separately estimates about 350 indirect jobs.[17] Those indirect jobs are not FTI vacancies. |
| El Paso, Texas | FTI’s November 4, 2025 announcement describes an $81.6 million investment and a 500,000-square-foot Excellerate factory at Pellicano Industrial Park. FTI named itself prime contractor and forecast operation in late spring or early summer 2026.[23] That target has passed; an actual opening was not confirmed in this review. |
| Opelika, Alabama | The Alabama Department of Commerce announced on February 25, 2026 that FTI planned to spend more than $79 million converting the former JoAnn Stores Distribution Center. It projected about 200 full-time jobs and an average annual wage above $65,000.[42] The wage is an announced project average, not an offer for every role. Opening status remains unverified here. |
| Olathe, Kansas | Johnson County Post reported on August 25, 2026 that the council approved up to $239.8 million in industrial revenue bonds and a 10-year, 80% property-tax abatement for three proposed manufacturing facilities. It reported a company forecast of 1,153 jobs over 10 years and no supplied construction timeline.[41] Treat this as an incentive and expansion report, not evidence that all buildings are operating or the bonds have been issued. |
For Pittsboro, Opus’s April 9, 2026 announcement identifies a useful division of responsibility: Opus sold the 47-acre site and was completing grading, access roads and utilities; FTI was serving as general contractor for its factory.[48] Ask which party owns the specific work before approaching either company. Current package availability remains unverified.
Monroe’s later company groundbreaking release, published August 5, 2026, names ARCO National Construction as the design-build partner and retains the spring 2027 completion expectation.[21] The release does not identify open subcontract packages.
The El Paso state accessibility record adds a narrower view. TABS2026001805 names Faith Technologies Incorporated as owner of a 499,854-square-foot warehouse shell at 12940 Pellicano Drive, with an estimated cost of $36 million. Its displayed completion date is June 1, 2026 and status is “Review Complete.”[40] That accessibility-review status is not proof of construction completion or occupancy. The shell estimate also measures a different scope from the company’s $81.6 million investment announcement.
Olathe already has an Excellerate manufacturing presence. FTI’s undated case study describes a 2.16-megawatt rooftop solar installation on an Excellerate building there.[50] It does not identify that building as one of the three proposed 2026 additions. Keep the existing facility and the expansion proposal separate when requesting a site or delivery address.
For Olathe, the underlying August 4 city report identifies applicants 167 Olathe 4, LLC and 167 Olathe 5, LLC and an approximately 1.5-million-square-foot proposal on 118.08 acres.[44] That report preceded the August 18 action described by the newspaper. Confirm the issued contracting entity and individual building schedule rather than treating the landholding names as verified FTI subsidiaries.
Olathe planning update: The City Council approved acceptance of public easements and street right-of-way for FTI Manufacturing (FP26-0016) on October 20, 2026. The city record describes three lots and four tracts on approximately 125.47 acres southwest of West 167th Street and South Lone Elm Road. It identifies utility and sanitary-sewer easements and rights-of-way along existing and future roads. This advances the land and infrastructure process; it does not establish that a construction package is open or a factory is operating. Confirm the building, access requirements and responsible buyer before committing estimating time. City of Olathe action G26-5971.
Documented work beyond factory expansion
FTI lists work in data centers, healthcare, industry, renewable energy, science and technology, transportation and entertainment.[29] The projects below show how shop work, controls and field installation connect. Unless another source is named, these are FTI’s accounts of its work. We have not audited its performance claims.
Meta’s Richland Parish campus, Louisiana. DPR’s December 13, 2024 announcement names US Engineering and Faith Technologies among trade partners for mechanical and electrical systems. DPR described its own initial scope as four data halls and a network building.[45] This supports Faith’s participation in the original build, not a claim to every later Hyperion expansion package. Use the Hyperion contractor and jobs guide for the broader project and builder routes.
Grande Cheese, Brownsville, Wisconsin. FTI describes design assistance and electrical installation for a 30,000-square-foot fresh-cheese plant expansion, including three production lines and processing equipment, with Boldt as general contractor.[36] The example is relevant to food-processing and equipment-integration suppliers.
Overland Park Regional Medical Center, Kansas. FTI describes prefabricated overhead racks, electrical installation and coordination with a mechanical contractor on multi-trade assemblies. The work involved fitting out third-floor shell space and planning three electrical shutdowns in a live hospital.[37] For trade partners, the useful precedent is coordination of assembly interfaces and shutdown work. The undated case study is not a current bid notice.
Confidential data-center trestles, multiple states. FTI reports designing and installing overhead power-conveyance trestles using modular 50-foot sections fabricated through Excellerate.[38] The source leaves the customer unnamed. It cannot identify those systems as Meta Hyperion or El Paso work.
Industrial controls and distribution. FTI’s project index lists furnace-control work at Logan Aluminum in Russellville, Kentucky; process power and controls at Novelis in Guthrie, Kentucky; and electrical installation for Ferguson’s warehouse in Lebanon, Tennessee.[2] These are selected portfolio references. Ask for a matching project contact and current specification before using them to qualify a product substitution.
FTI’s separate El Paso factory should not be confused with Meta’s campus in northeast El Paso. The Meta El Paso guide covers the campus’s named general contractors and the limits of its Faith attribution. The data-center project finder helps compare other projects without treating factory hiring as campus hiring.
Jobs and apprenticeship
FTI’s careers page provides separate routes for apprentices, electricians, manufacturing, engineering, office roles, internships and pipefitters.[20] Use the employer’s application route for employment. The general contact form and a supplier introduction are different channels.
Its apprenticeship page offers two tracks: licensed electrician and specialty systems technician. FTI advertises in-person and online classes, jobsite mentors and paid classroom training.[14] A program description does not reserve a place in the next class or grant a state license. Ask Talent Acquisition how to enter the program. Check class schedules and license rules for your state.
One concrete recruitment record was checked on November 9: Electrical Apprentice/Low Voltage Apprentice, R11336. The visible page displayed Nationwide, multiple additional locations and an Apply control. Its public record supplied a startDate of October 8, 2026; that field is not a verified first-ever posting date.[47]
The role prefers a high-school diploma or GED. It lists enrollment in Faith Apprenticeship Level 1 under experience. Travel is 60–75%. The usual work window is between 6 a.m. and 6 p.m., Monday through Friday. Nights, weekends and holidays are possible. Employment depends on passing a background check and drug test.[47] Ask how to meet the enrollment requirement before treating this as an entry-level offer with no prerequisites. The listing does not confirm how many jobs remain or assign you to a named data center.
For Monroe, Louisiana’s June announcement advertised entry-level positions starting at $22 an hour and linked a hiring-notification route.[17] That is dated expansion guidance, not a verified wage for R11336 or a promise of immediate employment. Compare the current requisition, location, travel requirement and written offer.
A training-development plan also changed. FOX 11 reported on February 17, 2026 that FTI decided against buying the former UW-Oshkosh Fox Cities campus after its due-diligence period. The company said it would explore other collaboration, including possible leasing.[43] Do not describe the earlier acquisition proposal as an operating FTI training campus.
Ownership and what remains unresolved
FTI’s corporate history says Town & Country Electric and SKC Electric were bought back from Encompass Services Corporation in 2002 and became divisions of Faith Technologies, Inc., operating under team-member ownership.[9] That is a dated company account, not a current shareholder register.
FTI’s October 6, 2026 release describes the business as privately held and reports its No. 21 position on Deloitte’s Wisconsin 75 list. Its homepage identifies Michael J. Jansen as CEO and chairman.[26][1] Those statements do not establish his equity stake, a current ownership percentage for employees, or a 100% ESOP structure. This review did not establish a current complete ownership chain or independently verify a private-equity sponsor.
Brand history, job advertisements and project records also do not replace jurisdiction-specific contractor-license checks. Before awarding regulated work, verify the exact entity, qualifier and license for the state and trade involved. This guide does not certify a nationwide license footprint.
Sources, updates and corrections
This review combines company project and commercial documents, public economic-development announcements, a Texas accessibility record, an Olathe agenda report, DPR’s project announcement and selected local reporting. Company production and performance claims remain attributed. The expansion review is selective; it is not a complete facilities, vacancies, contract-award or regulatory inventory. The November 9 competitive revision adds the Pittsboro construction responsibilities, completed-facility context and supplier decision record. It does not refresh the dates of the underlying announcements.
For a supplier, the next useful step is to identify the factory or jobsite and obtain the applicable quality requirements and issued order terms. For a worker, use the official careers route and resolve location, travel and apprenticeship entry before applying. Recheck dated listings and expansion milestones before making a commitment.
If you need a company or market comparison for a sourcing decision, discuss custom research with Echelon Reports. We agree on the evidence, coverage, deliverables, timing and price before starting a commissioned assignment.[52]
For a correction or to supply additional information, contact Echelon Reports with the company or project name, a dated source and the passage concerned. We review supporting evidence before changing the guide.
Sources
Sources accessed November 9, 2026. Publication and event dates are stated beside the claims where available. Undated corporate pages describe the material reviewed, not a new event.
- Faith Technologies Incorporated (FTI) – Leading with Energy
- FTI Projects – Electrical Installation, Energy, Manufacturing & More
- FTI Introduces Excellerate Products – FTI
- PURCHASE ORDER TERMS & CONDITIONS
- Excellerate Products General Terms and Conditions – FTI
- Company History – FTI
- Governor Braun Welcomes Faith Technologies Incorporated, 200 New Jobs to Pittsboro
- Electrical Apprenticeship Programs – FTI Careers
- Faith Technologies Incorporated™ to Power Northeast Louisiana Growth With $80.5 Million Investment – LED | Louisiana Economic Development
- FTI Careers
- Community Leaders Celebrate Groundbreaking for FTI’s New Manufacturing Facility in Monroe – FTI
- Purchase Order Terms & Conditions – FTI
- FTI Expands in El Paso, Creating 200 Jobs – FTI
- FTI Ranks No. 21 on Deloitte’s 2026 Wisconsin 75 – FTI
- Contact Us – FTI
- Terms & Conditions – FTI
- Services & Solutions – FTI
- Grande Cheese – FTI
- Overland Park Regional Medical Center – FTI
- Confidential Client: Overhead Conveyance Trestle – FTI
- TDLR TABS – Project Details
- Olathe OKs incentives for 3 data center equipment plants
- Faith Technologies to invest $79 million in Opelika manufacturing expansion – Made in Alabama
- Faith Technologies backs away from buying former UW-Oshkosh Fox Cities campus
- City of Olathe – File #: G26-5894
- DPR Brings Mission Critical Expertise to Meta AI… | DPR Construction
- FTI: Electrical Apprentice/Low Voltage Apprentice R11336
- Pittsboro expansion: Opus site infrastructure and FTI general contractor
- Excellerate Little Chute manufacturing facility
- Excellerate Olathe rooftop solar project
- Echelon Reports: research and custom reports
- City of Olathe action G26-5971: October 20, 2026 easements and street right-of-way acceptance
November 11, 2026 update: Added the October 20 Olathe easement and street right-of-way action. It is a planning milestone, not an open construction package or an operating factory.