Microsoft HR Ranch Road data center: status and contractors

Microsoft’s HR Ranch Road project in east Cheyenne has a named general contractor, JE Dunn, and a documented site identity: CYS43 at 6401 HR Ranch Road, Lot 2, Block 1, Bronco Subdivision.[1][22] Those identifiers give contractors a precise starting point for a scope inquiry. Cheyenne records site-plan approval on April 17, 2026, and Wyoming regulators approved the Bronco substation application on June 11; neither establishes an opening date.[21][25]

Contractors: use JE Dunn’s project mailbox and trade-partner qualification route below to ask who purchases your scope. Tradespeople: start with the employer board and Local 415 referral information. The retained union call is historical, and the October 30 public bid-board check found no HR Ranch, Bronco Filly or CYS43 entry.[10][15]

Project facts

Question Supported answer
Where is it? The CYS43 site plan gives 6401 HR Ranch Road, Cheyenne, Wyoming, and Lot 2, Block 1, Bronco Subdivision. This is a documented project address, not reporting instructions or a verified site entrance.[22]
Who owns and builds it? The city certificate names Microsoft Corporation Land Development Team as owner. Microsoft names JE Dunn as general contractor.[1][22]
What is approved? Cheyenne’s case timeline records site-plan approval April 17, 2026. PSC minutes record approval of the Bronco 115 kV substation application June 11, 2026.[21][25]
What construction has been observed? Cowboy State Daily’s September 25, 2026 photo captions describe HR Ranch construction as well underway. This is dated reporting, not an October site inspection.[11]
How large is it? JE Dunn describes its confidential Bronco Filly first building as 250,000 square feet and 48 MW, with five colos. Those are builder-described figures, not an owner-confirmed total for the HR Ranch campus.[18]
When will it open? No current opening date was verified. The utility forecast full substation service in Q2 2027; that is a different milestone from building completion or data center operation.[1][24]
What does it cost? The utility estimated approximately $39 million for the Bronco substation project. No total campus construction budget was verified.[24]
Are bids or jobs available? No project-specific open package or current craft vacancy was verified. Qualification and regional worker routes are listed below.[10][17]

Bronco Filly: connecting the names and building scope

The public records give contractors more than a directory alias. Cheyenne’s certificate names Microsoft, CYS43 and Bronco Subdivision together, while the attached plan supplies the HR Ranch Road address.[22]
The plan also displays Burns & McDonnell and Civil Design Advantage and labels five colos.[22]
A 2023 Army Corps document includes a field map labeled CYS43 Bronco-Filly in Cheyenne.[23]

JE Dunn calls its Bronco Filly project the initial phase of a multi-building Cheyenne campus and names Burns & McDonnell as architect.[18]
The builder describes a single-story facility with an air-cooled system, a pre-engineered metal building, administrative space and a full interior fit-out using owner-furnished equipment.[18]
Its five colos contain multiple data halls, and the site preparation included more than one million cubic yards of earth moved.[18]

Source What it establishes What it does not establish
Microsoft project page JE Dunn is general contractor for HR Ranch Road.[1] Building dimensions or a current package list.
Cheyenne case PUDC-26-22 and attached plan Microsoft, CYS43, Bronco Subdivision, 6401 HR Ranch Road and the recorded site-plan approval.[21][22] Issued building permits, completed inspections or an operating facility.
Army Corps determination A field map uses CYS43 Bronco-Filly for the Cheyenne site.[23] A local building permit or approval of every construction activity.
JE Dunn portfolio Bronco Filly’s first-building design, 250,000-square-foot area, 48 MW description and Burns & McDonnell role.[18] An explicit owner/address cross-reference tying those figures to the city’s Lot 2 approval.
PSC notice and minutes Microsoft’s Bronco substation application, estimated utility cost and recorded commission approval.[24][25] Actual energization, available utility packages or the signed order’s complete terms.

Echelon assessment: The shared CYS43 and Bronco identifiers, address and design team strongly support the connection between the city record and JE Dunn’s project. The builder’s dimensions concern its first building; confirm the building and package number before pricing work. Its 48 MW figure is not a verified campus total.

Approvals, construction evidence and the service forecast
April 17, 2026City case timeline records CYS43 site-plan approval. Building permits are separate.Cheyenne case [21]
June 11, 2026PSC minutes record approval of the Bronco substation application. Not proof of energization.Commission minutes [25]
September 25, 2026Local photo captions describe HR Ranch construction underway.Cowboy State Daily [11]
Q2 2027Full substation service forecast in the March application notice. Not a confirmed data center opening.PSC notice [24]

Different milestones, not a single construction schedule. Sources reviewed October 30, 2026.

Construction status and the conflicting dates

Microsoft’s project page combines approximately 18–24 months of construction with heavy earthwork anticipated for July–November 2025 and overall completion targeted for early 2026.[1]
Data Center Dynamics repeated those statements in its August 15, 2025 report.[2]
The owner page does not reconcile the duration with that target.[1]

Baxtel projects early-2027 completion.[3]
JE Dunn’s related-project card displays 2028 beside Bronco Filly, but does not define that year as a completion or opening milestone.[18]
These dates should not be combined into a new schedule.

The latest dated HR Ranch construction observation recovered for this report is Cowboy State Daily’s September 25, 2026 caption.[11]
Microsoft explicitly warns that completing construction does not mean the data center is operating or available.[1]
That distinction is missing from Data Center Map’s early-2026 operational projection.[7]

What the city approval covers

Cheyenne’s case timeline records April 17, 2026 approval of site plan PUDC-26-22.[21]
The certificate says engineering and building-plan reviews are separate, and the project remains subject to building permits and properly licensed contractors.[22]
It also requires a site plan for future phases or buildings and drainage and landscaping conditions before occupancy.[22]
An issued building-permit inventory was not recovered in this review.

The certificate’s signature line reads April 16, 2006, while its submission and expiration dates concern 2026 and 2028. This report uses April 17, 2026 from the city’s separate case timeline; the certificate’s inconsistent line remains unresolved.[21][22]

Bronco substation: approval is recorded, service is still a forecast

Wyoming PSC Docket 20003-266-EN-26, Record 18087, covers Cheyenne Light, Fuel and Power, doing business as Black Hills Energy, and its proposed Bronco 115 kV substation.[24]
The March 23 notice says the utility filed on March 13 to serve Microsoft’s new campus in southeast Cheyenne.[24]
It estimated approximately $39 million, payable by Microsoft through direct payments or a levelized fixed charge under a Facility Expansion Agreement.[24]

The commission’s June 11, 2026 minutes record unanimous approval of the application, effective immediately.[25]
They require the utility to notify the commission before placing additional transformers in the substation.[25]
The minutes were accepted and approved on September 30.[25]
They establish the commission’s recorded decision; the separately issued order and its complete terms were not recovered.

Milestone or figure Source and meaning
March 13, 2026 Application filed, according to the PSC notice.[24]
June 11, 2026 Commission approval recorded in the official minutes.[25]
June 16, 2026 Effective date requested in the application notice, not the actual meeting date.[24]
Q2 2027 Utility’s forecast for full substation service, stated in the March notice. Actual energization remains unverified.[24]
12 / 30 / 48 MW NPM reports forecast load by the end of 2027, 2028 and 2029 respectively. These are reported load forecasts, not measured consumption or confirmed building output.[19]

The substation design includes twelve 115 kV terminals: six for transmission ties, two for transformers serving customer load and four reserved for future use.[24]
The notice also describes transmission conductors, steel structures, concrete drilled-pier foundations, controls and metering.[24]
For firms serving those scopes, the practical question is who purchases the utility work separately from the building work. Approval and design scope do not mean those packages remain open.

Contractor routes

Microsoft publishes project manager Jake Coutts and HRRanch@jedunn.com for construction questions.[1]
It separately lists CheyenneDC@microsoft.com for community questions.[1]
Ask the project mailbox for the correct purchasing contact; it is not advertised as a bid-submission or recruiting inbox.

JE Dunn’s trade-partner page directs firms to TradeTapp within BuildingConnected for required prequalification.[4]
The questionnaire reached a sign-in page in the October 30 check.[9]
The linked public bid board displayed projects and deadlines, but the retrieved list had no HR Ranch, Bronco Filly or CYS43 entry.[10]
Private invitations and work bought through a subcontractor may not appear there.

Contractor checklist: confirm the site and package, identify the purchasing company, and review scope and terms before estimating.
Echelon’s pre-estimate checklist. Use the verified contractor routes to identify the buyer; this graphic is not a bid notice. View full-size graphic.

Before spending time on an estimate

Record Decision it supports
Site, building and package number Confirms the right project and phase.
Purchasing company and named contact Identifies whether JE Dunn, a trade contractor or a utility buyer controls the work.
Open scope, documents and deadline Separates a pricing request from general registration.
Qualification, safety and insurance requirements Tests whether the firm meets the package conditions.
Start date, duration and crew requirements Tests staffing and mobilization fit.
Payment terms and contracting entity Supports credit review before committing resources.

Worker routes

JE Dunn’s careers page links its Skilled Trades section; the official Craft board reviewed on October 30 did not name HR Ranch Road.[13][17]
Check the employer, location and assignment before arranging travel.

Route What the source offers Campus limitation
JE Dunn Craft careers Employer-listed skilled-trades jobs.[17] No HR Ranch posting verified in the displayed list.
Wyoming Electrical JATC Cheyenne and Casper apprenticeship program areas; statewide travel may be required.[14] Training, not a campus job offer.
IBEW Local 415 job calls Referral instructions and a recorder for current calls.[15] Captured page dated September 3, 2026; not current vacancy confirmation.
Western States Carpenters Regional contractor hiring information.[16] The JE Dunn entry names the University of Wyoming, not HR Ranch.

The retained Local 415 page lists an Intermountain Electric call for CYS-43/Various in Cheyenne.[15]
The city record now places CYS43 at HR Ranch Road, but the dated call includes “Various” and does not establish a current opening or the employer’s precise campus scope.[22]
Confirm the assignment and remaining demand with the hall before treating it as an HR Ranch job.

Keep other Cheyenne projects separate

Microsoft’s April 14, 2026 expansion announcement concerns approximately 3,200 acres near Wapiti Trail and Bison Business Park.[8]
Its more than $68 million in completed and future off-site improvements applies across Cheyenne, not to HR Ranch’s construction budget.[8]
Data Center Dynamics’ reference to more than 920 acres at North Range Business Park is also regional background.[2]

Cowboy State Daily’s September 25 story describes two legal challenges involving the Highlands annexation and a related council action.[11]
Its HR Ranch construction photographs do not make that dispute an HR Ranch lawsuit. The current court docket was not inspected for this report.

Research for a contracting decision

Use the qualification route and project contact above to establish whether there is work your firm can pursue. Compare other projects through the Echelon data center project reports.

Method and update note

Research: Echelon Reports. Editorial contact: Mike Warner. Editorial revision November 3, 2026; source observations remain October 30. The report connects the city’s CYS43 address and site-plan record with the PSC’s recorded June 11 substation approval. Historical schedule statements retain their original dates.

Evidence includes owner and builder statements, government records, reporting and directory entries. Echelon’s interpretation is labeled. The review did not include a site visit, private bid documents, project-team interview or complete subcontractor roster.

Sources

  1. Microsoft: HR Ranch Road datacenter construction
  2. Data Center Dynamics: Microsoft breaks ground in Cheyenne (August 15, 2025)
  3. Baxtel: HR Ranch Road campus listing
  4. JE Dunn: current trade-partner process
  5. Data Center Map: Microsoft HR Ranch Road
  6. Microsoft: proposed Cheyenne expansion (April 14, 2026; updated June 8)
  7. JE Dunn TradeTapp sign-in route
  8. JE Dunn public bid opportunities
  9. Cheyenne Woman Asks Court To Overturn 3,500-Acre Microsoft Data Center Annexation
  10. Careers | JE Dunn Construction
  11. Casper or Cheyenne Program Area
  12. Current Job Calls
  13. Wyoming Recruitment – Western States Carpenters
  14. JE Dunn Craft careers board
  15. Data Center Construction in Cheyenne, WY | JE Dunn
  16. T&D: Microsoft to pay for new transmission infrastructure to serve data center expansion in Wyoming’s capital
  17. Cheyenne: CYS43 Bronco site-plan case
  18. Cheyenne: CYS43 certificate and approved site plan
  19. USACE: Bronco-Filly jurisdictional determination
  20. Wyoming PSC: Bronco substation application notice
  21. Wyoming PSC: June 11, 2026 meeting minutes

Echelon Trades Jobs

Hiring or looking for work in the trades?

Employers can submit an opening for review. Tradespeople can tell us what work they want. Both are free, and worker profiles stay private.

Post a free job Tell us what work you want

Visit Echelon Trades Jobs