Hoffman Estates data center: status, contractors and jobs

Compass Datacenters is building five data centers on the former Sears headquarters property in Hoffman Estates, Illinois.[1] Chicago Construction News reported on October 27, 2026, that Power Construction had topped out the fifth and final building, with completion targeted for 2027.[3]

Power’s role in above-ground construction makes its subcontractor qualification process a useful starting point for firms seeking work.[5][12] For tradespeople, its two retained union job descriptions offer employer contacts, but neither names this campus.[13][14] Confirm the assignment and remaining scope before pricing work or arranging travel.

Contractors: Check the documented roles, then use the qualification checklist. Workers: Go to employer listings and training.

Project facts

Question Source-backed answer
Where is it? The former Sears headquarters property at Beverly and Higgins roads, near I-90 west of Illinois Route 59.[2] The February 2025 village agenda identifies 5400-5600 Trillium Boulevard, formerly 3333 Beverly Road.[11] Confirm the reporting entrance with your employer.
Who is developing it? Compass Datacenters, which says it acquired the property in September 2023.[1]
How large is the campus? Five buildings on 197 acres, according to the village. Compass described nearly 200 acres.[1][2] See the acreage explanation below before comparing reports.
What is the latest milestone? The fifth building topped out, according to the October 27, 2026 report. Work continued across all five buildings.[3] October 27 is the report date, not a separately verified ceremony date.[3]
When will it open? The report targets completion and a ribbon-cutting in 2027. It does not give a confirmed operating date for each building.[3]
Is power delivery confirmed? ComEd forecast mid-2026 substation energization in June 2024.[8] This review did not establish that energization occurred.
Hoffman Estates construction timeline from the 2023 acquisition to the reported fifth-building topping-out and 2027 completion target.
Reported milestones, not a construction schedule or proof of operating capacity. Sources: Compass, the village, Daily Herald and Chicago Construction News. The same chronology appears in the text below. October 27 is the publication date of the topping-out report, not a separately verified event date.

What has been built, and what remains uncertain

Compass announced the five-building development in June 2024, after acquiring the property the previous September.[1] By November 2024, the village had approved mass grading and Compass had contracted Power Construction for above-ground construction, according to the Daily Herald.[5]

Village Board minutes record approval of the campus plat and site plan on February 17, 2025, through Ordinance #5152-2025.[21] Separate minutes record approval of the ComEd substation site plan at 5700 Trillium Boulevard on June 16, 2025, through Ordinance #5170-2025.[22]

In September 2025, Village Manager Eric Palm told the Daily Herald that the first building’s core-and-shell permit had issued.[6] The newspaper reported construction of the first two shells, the substation foundation and utility connections in December 2025.[7]

The newer October 2026 account reports that all five buildings had topped out, with work continuing toward the 2027 target.[3] The report does not establish finished interiors, commissioned equipment or an occupied campus.[3] In its earlier reporting, the Daily Herald explicitly distinguished shell permits from interiors designed around a tenant’s requirements.[7]

Named companies and their roles

The documented roles below identify which company to approach. They do not constitute a complete subcontractor roster.

Organization Documented campus role What to confirm before pursuing work
Compass Datacenters Developer; announced the five-building program in June 2024.[1] Which company controls the specific purchase, and whether it concerns a building shell or customer fit-out.
Power Construction Named for above-ground construction in November 2024 reporting and for the fifth-building topping-out in October 2026.[5][3] Current package status, buying contact and whether your company must qualify before receiving plans.
American Demolition Named by Compass and the village for demolition and material recovery.[4][2] Whether any relevant scope remains. Its historical role does not establish a current vacancy or new-building installation award.
ComEd Announced infrastructure upgrades and a new on-site substation in June 2024.[8] The service milestone relevant to your work. An announced utility project does not identify its electrical subcontractors.

The reviewed sources do not identify a complete electrical, mechanical, plumbing, fire-protection or commissioning roster. Ask Power which firm controls your scope at Hoffman Estates.

Contractor routes

Power’s subcontractor partners page requires initial company qualification and periodic updates to its subcontractor and supplier database.[12] Use the current “Start the qualification process” link on that page, rather than an old saved form. The published process is company qualification, not a campus bid invitation.[12]

Prepare Power’s published requirements
Identity and financials Signed W-9; three years of financial statements and notes prepared by a third party. The latest statement should cover a period ending within the preceding six months.[12]
Insurance and bonding Sample insurance certificate showing coverage and limits; aggregate and per-project bonding capacity.[12]
Safety records Three years of workers’ compensation experience-modification history and corresponding OSHA 300A reports, where applicable.[12]
Capacity and affiliations Current work and backlog; applicable union good-standing letters and business-certification letters.[12]

Before you price a package

Ask the project contact to confirm:

  1. The purchasing company, building and exact trade scope.
  2. Whether the package is unawarded, being priced or already under contract.
  3. Who issues plans and addenda, and the bid deadline.
  4. Required supervision, mobilization date, shift and expected duration.
  5. Insurance, bonding and payment terms for that package.

Send your trade, relevant project experience and available capacity with the inquiry.

Compass provides a general contact form requesting company, title and reason for the inquiry.[18] Use it to ask who controls a specific scope when buying responsibility is unclear.

Worker routes

Power’s concrete carpenter and laborer descriptions displayed 8750 W Bryn Mawr Ave, Chicago, when checked on October 30, 2026.[13][14] Neither names the Compass campus, gives a campus reporting location or publishes a wage for that assignment.[13][14] Treat them as employer-level leads, not confirmed Hoffman Estates openings; do not travel to the displayed address without reporting instructions.

Employer listing Published work and requirements What remains unconfirmed
Union concrete carpenter, #479, posted April 14, 2026 Concrete formwork, blueprint reading, tool use, dismantling forms and safety procedures. Calls for carpentry proficiency and construction knowledge.[13] Campus assignment, pay, start date and whether the employer is still filling this position.
Union laborer, #443, posted March 31, 2026 Material handling, concrete assistance, grading, traffic control and cleanup. Lists a high school degree or equivalent, apprenticeship participation and union laborer status.[14] Campus assignment, pay and current hiring need. The stated requirements do not describe unrestricted beginner entry.

Before making travel or housing commitments, confirm the reporting location, start date, expected duration, shift, wage classification and any travel allowance.

Training for readers entering a trade

These regional programs are separate from Compass hiring. Admission does not establish placement on this campus.

Program Entry information from its own page
Pipefitters Local 597 Training Fund Starts with an Application Day reservation at Mokena. Requirements include minimum age 17, work eligibility, diploma or GED documentation, a driver’s license copy and a $20 application fee. High school seniors may submit an “on track” letter. Testing and selection follow.[15]
Mid-America Carpenters Chicago-area training General carpentry and concrete-form-builder applications open during specified periods announced through the Elk Grove Village page. Entry requires Illinois residency, minimum age 17 and a $25 processing fee; prior jobsite or tool experience is not required.[16]
Electrical Joint Apprenticeship and Training Trust Describes Local 134 electrical apprenticeship and career paths, including data-center work. Check the program’s admissions instructions for current eligibility and intake; this overview does not establish an available seat.[17]

Investment, jobs and power: keep the measures separate

Compass’s June 2024 announcement forecast approximately $10 billion in local investment once the campus becomes operational.[1] It did not disclose an amount already spent or the value of contracts still available.[1] The same announcement forecast 1,000 local construction jobs, not 1,000 current vacancies.[1]

The October 2026 construction report describes a lunch and raffle for more than 800 workers involved in the project.[3] That event count measures participation, not current openings.

The Chicago Sun-Times reported a $194 million property sale and a $367 million Citizens Bank loan in November 2023.[9] Those are historical transaction figures, not a current financing balance.

ComEd’s mid-2026 energization date was a forecast in its June 2024 announcement.[8] The village’s substation approval establishes a separate milestone, not proof of live power.[2] This review did not recover utility confirmation of energization or a disclosed customer lease. The December 2025 report’s reference to a future tenant is dated evidence, not proof the campus remains unleased today.[7]

What would change the work outlook

Next evidence to obtain Decision it would support Current boundary
A dated package invitation from the responsible buyer Whether your company should price a specific scope No open campus package verified in this review.
An employer-confirmed assignment with terms Whether to accept work or arrange travel The two Power descriptions do not name this campus.[13][14]
A utility energization notice or service confirmation Whether the relevant power milestone has occurred The retained ComEd source gives a forecast, not completion.[8]
A tenant disclosure and building-specific fit-out scope Which interior systems and trades the customer requires No disclosed tenant contract recovered; shell construction alone does not answer this.[7]

Site identity questions

Why do reports give different acreage figures?

The village describes a 197-acre Compass campus, while Compass’s announcement rounds it to nearly 200 acres.[2][1] The Daily Herald’s December 2025 report uses 273 acres for the former Sears property.[7] The Sun-Times described a sale of 197 acres from the larger Sears holding.[9] This report uses the village’s campus figure, not an independently reconciled parcel survey.

Was the Hoffman Estates data center project withdrawn?

The village says H.E. Holdings withdrew its rezoning application for Plum Farms at 4800 W. Higgins Road on June 30, 2026.[10] That notice concerns a different property, not Compass’s former Sears campus.[10][2] The later October report describes construction progress at Compass.[3]

Work and hiring through Echelon

Looking beyond these employer listings? Tell Echelon your trade, experience and preferred location through the private worker-interest form. It is not an application to Compass or Power.[20] Echelon requires separate permission before sharing your details with a named employer or recruiting partner, as explained in its jobs privacy terms.[19]

Employers can submit a free trades job for review.[23] The submission page asks for the employer, work location, requirements, application route, and pay and travel terms.[23] Submissions are reviewed before publication.[19]

Compare other locations through Echelon’s data center construction reports and project finder.

Sources and method

Editorial revision November 3, 2026; source observations remain October 30. Echelon compared owner and utility announcements, village records, construction reporting, and employer and training pages. The latest topping-out account comes from Chicago Construction News.[3]

The review did not recover a complete current permit register, confirmed energization, tenant contract, trade-award schedule or campus-specific hiring roster. Village Board minutes establish the campus and substation site-plan approvals.[21][22]

  1. Compass Kicks Off Development Of Its First Campus in Illinois
  2. Compass Datacenters
  3. Power Construction tops out fifth data centre building in Hoffman Estates
  4. Extending green construction concepts to a brownfield site
  5. Sears demolition continues even as Hoffman Estates site begins prep for Compass Datacenters
  6. Compass Datacenters ready to build on cleared Sears headquarters site in Hoffman Estates
  7. After Sears teardown, walls are going up for Hoffman Estates data center campus
  8. ComEd, Compass Datacenters Kick Off New, State-of-the-Art Data Center to Transform Former Sears Headquarters Site (same ComEd release at Nasdaq)
  9. Compass Datacenters hopes business will hum at ex-Sears site in Chicago
  10. Petitioner withdraws rezoning application for Plum Farms property
  11. Village Board of Trustees • Agendas & Minutes
  12. Subcontractor Partners | Power Construction
  13. Union Concrete Carpenter
  14. Union Laborer
  15. Applications – Pipefitters' Training Fund
  16. Chicago, IL
  17. Career Paths Through Apprenticeship
  18. Contact Us – Compass Datacenters
  19. Jobs service privacy and listing terms
  20. Tell us what work you want
  21. Village Board minutes, February 17, 2025
  22. Village Board minutes, June 16, 2025
  23. Post a free trades job: Echelon submission instructions

Echelon Trades Jobs

Hiring or looking for work in the trades?

Employers can submit an opening for review. Tradespeople can tell us what work they want. Both are free, and worker profiles stay private.

Post a free job Tell us what work you want

Visit Echelon Trades Jobs