PROJECT INTELLIGENCE · QUINLAN, HUNT COUNTY, TEXAS · NOVEMBER 17, 2026
Core Scientific reported in September that construction had commenced at its Hunt County campus. A November state registration adds a $1.3 billion estimated building, site and infrastructure scope at 4852 CR 3507 in Quinlan.[52][5]
For contractors, the immediate task is to reach the buyer for a defined work package. Core Scientific’s contact page is the owner-side starting point for that inquiry.[23]
The registration covers a 341,326-square-foot core-and-shell building. It lists a projected November 24, 2026 start and September 4, 2028 completion. The wider campus is planned for 285 MW of leasable capacity, with 110 MW assigned to AMD direct leasing in the latest company presentation.[5][6][12]
Hunt County project facts
| Item | Project evidence |
|---|---|
| Site | 4852 CR 3507, Quinlan, Hunt County, Texas.[5] |
| Registered scope | $1.3 billion estimated cost; one 341,326-square-foot core-and-shell building with site and infrastructure improvements.[5] |
| Registered dates | November 24, 2026 start; September 4, 2028 completion. Projected dates in the November 13 registration.[5] |
| Owner and designer | Telios Quinlan One, LLC; Gensler design firm.[5] |
| Wider campus | Approximately 265 acres; 285 MW leasable and 430 MW gross planned capacity in the March presentation.[6] |
| Hunt customer allocation | AMD direct lease: 110 MW in the November 5 contracted-power chart.[12] |
| Customer delivery forecast | Hunt initial delivery estimated for the first half of 2028 in the November 5 deck.[12] |
TDLR lists the tenant for this building as “Not Assigned”; the 110 MW AMD allocation is for the Hunt campus, not a documented assignment to this shell.[5][12]
The Texas Department of Licensing and Regulation (TDLR) record is an architectural-barriers registration with the status “Project Registered.” Its estimated cost and dates describe the registered scope. Building permits, utility delivery and construction progress follow separate approval and delivery processes.[5]
How to approach Core Scientific for construction work
Use the official contact form or 512-402-5233 to request the Hunt County construction procurement lead. Name your trade, the Quinlan address and the package contact or qualification instructions you need. This is a general owner inquiry channel; a package invitation and bid deadline must come from the responsible buyer.[23]
The registration names Telios Quinlan One, LLC as owner and Gensler as design firm. An October 6 Herald-Banner report identifies “Cadence” as overseeing construction, based on a meeting described by County Commissioner Garry Smith. Ask Core Scientific for Cadence’s full legal name and contracting scope before directing a qualification package there.[5][16]
Hunt County package inquiry worksheet
Copy these questions into your pursuit notes. Record the buyer’s answer, confirming document and date for each. Start with the scope information available, then refine the estimate as drawings and commercial terms arrive.
| Decision to settle | Documented starting point | Question for the responsible buyer |
|---|---|---|
| Buyer and package | TDLR names Telios Quinlan One, LLC; Core Scientific has a general inquiry route.[5][23] | Who issues the contract, for which building and package? Ask for the legal entity and procurement contact. |
| Construction management | The Herald-Banner identifies Cadence as overseeing construction.[16] | What is the full legal entity, appointment and purchasing authority for this work? |
| Scope and interfaces | The registration covers core-and-shell, site and infrastructure work.[5] | Which drawings, quantities and utility/customer-side boundaries apply? Request exclusions and addenda. |
| Schedule and access | Registered building dates and reported road arrangements have different source dates.[5][16] | What are the bid, award, access, delivery and acceptance milestones for this package? |
| Qualification and commercial terms | Core Scientific publishes supplier conduct standards.[22] | Which qualifications, safety, insurance, bonding, payment, retainage and change-order terms apply? |
Core Scientific’s supplier code of conduct describes supplier standards and compliance assessments. Ask the procurement lead which registration or qualification process applies to your package.[22]
Construction workstreams to investigate
The registered core-and-shell, site and infrastructure scope gives civil, concrete and enclosure firms a clear starting point. The work map below also covers the building systems needed for a data center. It is Echelon’s package-planning analysis; issued drawings and buyer documents will establish the actual quantities, boundaries and installers.[5]

| Workstream | Package questions |
|---|---|
| General contracting / construction management | Confirm coordination, package purchasing, site management and any self-performed scope. |
| Civil / excavation / roads | Establish earthwork, drainage, access, underground and road-improvement limits; obtain the current truck plan.[5][16] |
| Concrete | Request foundation, slab, equipment-pad and utility-structure quantities and placement milestones. |
| Structure / enclosure | Confirm frame, roofing, walls, weatherproofing and door packages against issued drawings.[5] |
| Electrical / utility | Separate incoming utility/substation work from customer-side switchgear, distribution and grounding; align energization stages.[11] |
| Plumbing / pipefitting | Confirm water, drainage, process-cooling piping and service connections. |
| HVAC / mechanical | Obtain cooling, ventilation and heat-rejection designs, equipment boundaries and operating conditions. |
| Fiber / telecom / security | Define outside plant, fiber pathways, network rooms and security-system responsibilities. |
| Fire protection | Confirm sprinkler, alarm interfaces, testing and approval responsibilities. |
| Controls / commissioning | Separate installation and contractor testing from owner assurance, integrated-system testing and turnover.[46][48] |
| Support / logistics | Ask about hauling, rentals, temporary services, waste, cleanup, security and workforce transport. |
Check the licensing requirements for the work you intend to perform. Texas regulates electrical contracting and air-conditioning/refrigeration contracting through TDLR. The plumbing board sets responsible master plumber, supervision and insurance requirements. Local permits and buyer qualifications also belong in the package review.[49][50][51]
Worker referrals, training and employer roles
For craft work or entry into a trade, use the regional referral and training routes below. Ask about jurisdiction, entry requirements, participating employers and the current call or intake. These organizations are regional starting points, rather than confirmed Hunt campus dispatch channels.
| Trade path | Official route | Purpose |
|---|---|---|
| Electrical | IBEW Local 20 jobs and apprenticeship.[28][29] | Referral/intake and apprenticeship information. |
| Plumbing, pipefitting and HVACR | UA Local 100 apprenticeship and contact.[31][33] | Training and the appropriate referral contact. |
| Labor / concrete-related work | LIUNA Local 154 training.[41] | Labor and civil/concrete-support training. |
| Equipment / hoisting | IUOE Local 178 directory.[34] | Equipment classifications and regional referral contact. |
| Sheet metal | DFW Sheet Metal JATC.[35] | Sheet-metal apprenticeship information. |
| Sprinkler fitting | Local 669 apprenticeship.[37] | Fire-suppression trade training. |
UA Local 100 publishes both an application page and an orientation/selection process. Confirm its current instructions before traveling to Mesquite.[31][32]
For experienced professional staff, the Core Scientific job board carries three inspected descriptions that include Hunt among eligible residence areas.[21] These are Operations Readiness Manager, Site Commissioning and Turnover Manager, and Low Voltage Designer. They cover portfolio or assigned-facility work, rather than identifying Hunt craft openings.[45][46][48]
The two manager descriptions combine a Remote listing with onsite-hours language and travel of up to 50%. Resolve the reporting site and travel with the employer. For any assignment, confirm the employer, base wage, overtime, duration, benefits, lodging or per diem and start instructions before making arrangements.[45][46]
What an assignment can mean in dollars
Regional pay provides a useful planning benchmark. These May 2025 BLS mean hourly cash wages cover the Dallas-Fort Worth-Arlington metropolitan area across industries. The annual examples multiply each hourly rate by 2,080 regular hours. Actual Hunt compensation and hours depend on the employer and assignment.[4]
| Regional occupation | Mean hourly cash wage | Illustrative annual gross |
|---|---|---|
| Cement Masons and Concrete Finishers (47-2051) | $24.22 | $50,377.60 |
| Construction Laborers (47-2061) | $21.05 | $43,784.00 |
| Operating Engineers and Other Construction Equipment Operators (47-2073) | $26.51 | $55,140.80 |
| Electricians (47-2111) | $28.83 | $59,966.40 |
| Plumbers, Pipefitters, and Steamfitters (47-2152) | $29.94 | $62,275.20 |
| Heating, Air Conditioning, and Refrigeration Mechanics and Installers (49-9021) | $29.69 | $61,755.20 |

At the regional electrician mean of $28.83 an hour, a 12-week assignment with 40 regular hours and 10 overtime hours a week, paid at 1.5 times base for overtime, would produce $19,027.80 in gross cash wages. The hours and overtime premium are chosen assumptions.[4]
Ten electricians working 22 weeks at 40 hours would earn $253,704 in combined gross cash wages. Ten concrete finishers at the regional $24.22 mean would earn $213,136 on the same schedule. These alternative crew examples show the value of sustained assignments without assuming a campus staffing plan.[4]
Contract receipts and profit
A hypothetical $1 million package with $930,000 in total costs leaves $70,000 before tax, a 7% margin. Here, costs include labor and employer burden, materials, equipment, subcontracting, insurance and overhead. An estimator needs the actual scope, schedule and terms to price a Hunt package.
Spending near work and back home
Consider a hypothetical commuter earning the annual electrician example of $59,966.40. Assume 25% goes to deductions, leaving $44,974.80 in take-home pay. Spending 20% of take-home near the site and 50% at home would put $8,994.96 near work and $22,487.40 in the home community. The remaining $13,492.44 goes to savings, debt or other uses. Deductions and those uses reconcile to gross pay.
Those shares illustrate how location changes who benefits. They are not measured worker behavior or a tax estimate. A project-wide net benefit would also depend on local participation, other employment, alternative land uses, incentives and public infrastructure costs. Contract receipts, supplier sales, payroll and household spending overlap and should not be added as separate benefits.
Schedule and site questions that affect the work
Building dates and customer delivery
The November 13 registration projects a November 24, 2026 building start and September 4, 2028 completion.[5] These building-scope dates follow the company’s September 10 report of campus construction and long-lead equipment orders.[52] The November 5 company deck separately forecasts initial Hunt customer delivery in the first half of 2028. Ask the buyer which building, utility and acceptance milestones govern your package.[12]
The same deck assigns 110 MW to Hunt’s AMD direct lease and approximately 192 MW to a separate “Power Pathways Under AMD Reservation” chart. The March campus plan describes 285 MW leasable capacity and 430 MW gross capacity, with power ramping from 2027 to 2029. Those figures describe different commercial and infrastructure boundaries.[6][12]
Road access and delivery planning
The October 6 Herald-Banner report describes trucks entering from FM 1564 using CR 3507 and leaving south toward FM 2101. It also describes a proposed company-funded improvement agreement for CR 3507 and CR 3508, including paving, widening and culvert work. Suppliers should obtain the current authorized truck plan and road-work interfaces from site management before dispatch.[16]
Power, water and approval records
Core Scientific’s November 5 filing reports an approved ERCOT interconnection ramp schedule for Hunt and a related electric-service agreement expected to support approximately 430 MW of gross utility capacity. Obtain the delivery stages and customer-side interfaces relevant to the package you are pricing.[11]
Texas’s August 3 audit directive concerns data centers advancing through grid interconnection. The later company filing discusses limited exposure for capacity already covered by agreements and the risks from future restrictions. Reporting on a possible future statewide moratorium is a policy proposal, rather than a Hunt-specific permit decision.[17][11][19]
For mechanical and infrastructure estimates, request the cooling design, water-service commitments and applicable approvals. The records reviewed here leave the executed road agreement, water entitlement and complete permit status unresolved. Those documents, along with dated progress and utility milestones, are the next useful additions to this report.
Compare projects and take the next step
Use the data-center construction hub to compare locations and work stages. The Abilene Stargate contractor report covers a separate Texas development. For another Texas procurement comparison, see the Project Matador contractor guide. For community decisions, read our guide to data-center costs, jobs and local trade-offs.
For a correction or to supply additional information, contact Echelon Reports with a dated source. For a research inquiry, identify the project, trade and decision you need help resolving so we can discuss scope and price.
Sources, calculations and review date
Echelon Reports research snapshot and editorial review: November 17, 2026. Source dates identify the events and forecasts they describe.
Employer descriptions were inspected November 17. Their ATS start fields are November 12 for the manager roles and October 8 for the designer; those fields do not establish a first posting date or remaining headcount. Regional wage and household examples are calculated illustrations, not a Hunt payroll forecast, wage offer or economic-impact study.[45][46][48]
- [4] BLS May 2025 Dallas-Fort Worth-Arlington occupational wages
- [5] Project Details
- [6] March 2, 2026 – EX-99.2 – 8-K: Current report | Core Scientific, Inc. (CORZ)
- [11] November 5, 2026 – 10-Q: Quarterly report [Sections 13 or 15(d)] | Core Scientific, Inc. (CORZ)
- [12] November 5, 2026 – EX-99.2 – 8-K: Current report | Core Scientific, Inc. (CORZ)
- [16] Core Scientific construction brings more traffic to area Hunt County roads
- [17] Governor Abbott Directs Comprehensive Data Center Audit | Office of the Texas Governor | Greg Abbott
- [19] Texas Tribune: Hinojosa proposed data-center moratorium, November 4, 2026
- [21] Core Scientific Jobs | Apply to Our Available Roles Today
- [22] Supplier Code of Conduct | Core Scientific Standards & Expectations
- [23] Contact Core Scientific | Speak With an AI Infrastructure Expert
- [28] Apprenticeship Program | IBEW Local 20
- [29] Job Openings for IBEW Local 20 | Apply Now
- [31] Local 100 | Apprenticeship
- [32] Local 100 | Application
- [33] Local 100 | Contact Us
- [34] Local 178
- [35] Home | DFW Sheet Metal JATC
- [37] Apprenticeship | Sprinkler Fitters Local 669
- [41] Apprenticeship & Training ⋆ LiUNA! Local 154 ⋆ Laborers in Arlington & Wichita Falls, TX
- [45] Core Scientific: Operations Readiness Manager
- [46] Core Scientific: Site Commissioning and Turnover Manager
- [48] Core Scientific: Low Voltage Designer
- [49] Electricians Homepage
- [50] Air Conditioning and Refrigeration Contractors Homepage
- [51] Responsible Master Plumber – Texas State Board of Plumbing Examiners
- [52] Core Scientific: September 10, 2026 power-status disclosure